Connect the Grid Act of 2026
S. 3976119th Congress

Connect the Grid Act of 2026

Introduced in the SenateSen. Edward Markey (D-MA)68 sections · 6 min read
Version: Introduced in Senate · Mar 3, 2026

Section 1. Short title

This Act may be cited as the Connect the Grid Act of 2026.

Section 2. Definitions

In this Act:

(1) Abandoned mine land

The term abandoned mine land means land, water, or a watershed that is contaminated or scarred by extraction, beneficiation, or processing of ores or minerals (which may include phosphate, but does not include coal).

(2) Brownfield site

The term brownfield site has the meaning given the term in section 101 of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (42 U.S.C. 9601).

(3) Commission

The term Commission means the Federal Energy Regulatory Commission.

(4) Electric Reliability Organization

The term Electric Reliability Organization has the meaning given the term in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a)).

(5) Environmental justice community

The term environmental justice community means a community with significant representation of communities of color, low-income communities, or Tribal and Indigenous communities that experiences, or is at risk of experiencing, higher or more adverse human health or environmental effects.

(6) ERCOT

The term ERCOT means the Electric Reliability Council of Texas.

(7) Grid-enhancing technology

The term grid-enhancing technology means a solution that increases the transfer capability of high-voltage transmission facilities.

(8) MISO

The term MISO means the Midcontinent Independent System Operator transmission organization.

(9) National Priorities List

The term National Priorities List means the National Priorities List developed by the President in accordance with section 105(a)(8)(B) of the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (42 U.S.C. 9605(a)(8)(B)).

(10) Registered apprenticeship program

The term registered apprenticeship program means an apprenticeship program registered under the Act of August 16, 1937 (commonly known as the National Apprenticeship Act; 50 Stat. 664, chapter 663; 29 U.S.C. 50 et seq.), that meets the standards of subpart A of part 29, and part 30, of title 29, Code of Federal Regulations (or successor regulations).

(11) Reliability standard

The term reliability standard has the meaning given the term in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a)).

(12) SPP

The term SPP means the Southwest Power Pool transmission organization.

(13) Total transfer capability

The term total transfer capability has the meaning given the term in section 37.6(b)(1)(vi) of title 18, Code of Federal Regulations (as in effect on the date of enactment of this Act).

(14) Transmission facility

The term transmission facility means a facility that is used for the transmission of electric energy in interstate commerce, including a transmission line.

(15) Transmission organization

The term transmission organization has the meaning given the term in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a)).

(16) Tribal and Indigenous community

The term Tribal and Indigenous community means a population of people who are members of—

(A) a federally recognized Indian Tribe;

(B) a State-recognized Indian Tribe;

(C) an Alaska Native or Native Hawaiian community or organization; or

(D) any other community of Indigenous people located in a State.

(17) Tribal government

The term Tribal government means the governing body of an Indian Tribe.

(18) Western Interconnection

The term Western Interconnection means the synchronously operated electric transmission grid located in the western part of North America, including parts of Montana, Nebraska, New Mexico, South Dakota, Texas, Wyoming, and Mexico, and all of Arizona, California, Colorado, Idaho, Nevada, Oregon, Utah, Washington, and the Canadian Provinces of British Columbia and Alberta.

(a) Application of part II of the Federal Power Act

Section 201(b)(2) of the Federal Power Act (16 U.S.C. 824(b)(2)) is amended—

(1) in the first sentence, by striking section 201(f) and inserting subsection (f); and

(2) in the second sentence—

(A) by striking 210, 211, 211A, 212,; and

(B) by striking an electric utility or other entity and inserting any entity that is otherwise exempt under subsection (f).

(b) Definition of public utility

Section 201(e) of the Federal Power Act (16 U.S.C. 824(e)) is amended by striking 210, 211, 211A, 212,.

(1) Section 212 of the Federal Power Act (16 U.S.C. 824k) is amended by striking subsection (k).

(2) Section 216 of the Federal Power Act (16 U.S.C. 824p) is amended by striking subsection (k).

(3) Section 217 of the Federal Power Act (16 U.S.C. 824q) is amended—

(A) by striking subsection (h); and

(B) by redesignating subsections (i) through (k) as subsections (h) through (j), respectively.

(4) Section 220 of the Federal Power Act (16 U.S.C. 824t) is amended by striking subsection (f).

(d) Technical conference

Not later than 180 days after the date of enactment of this Act, the Commission shall convene a technical conference to assist entities affected by the amendments made by this section with compliance with any requirements made applicable to those entities pursuant to those amendments, including by publishing the steps necessary for such compliance.

(a) Amendments

Section 215 of the Federal Power Act (16 U.S.C. 824o) is amended—

(1) in subsection (a)(3), in the second sentence, by striking enlarge such facilities or to construct new transmission capacity or generation capacity and inserting construct new generation capacity; and

(2) in subsection (i)(2), by striking or transmission.

(1) In general

Not later than 30 days after the date of enactment of this Act, the Commission shall order the Electric Reliability Organization to submit to the Commission a proposed reliability standard that requires minimum total transfer capability of—

(A) between 4.3 and 12.6 gigawatts between the area under functional control of ERCOT and the area under functional control of SPP;

(B) between 2.5 and 16.2 gigawatts between the area under functional control of ERCOT and the area under functional control of MISO; and

(C) between 2.6 and 7.9 gigawatts between the area under functional control of ERCOT and the Western Interconnection.

(2) Contents

The Commission may only approve a proposed reliability standard described in paragraph (1) if that reliability standard—

(A) requires minimum total transfer capability as described in paragraph (1); and

(B) requires each of ERCOT and SPP, ERCOT and MISO, and ERCOT and 1 or more neighboring balancing authorities in the Western Interconnection (as determined by the Electric Reliability Organization) to jointly submit, not later than 1 year after the date of enactment of this Act, a plan that—

(i) designates 1 or more entities to site and construct new transmission facilities, or modify existing transmission facilities, to achieve the applicable minimum total transfer capability; and

(ii) includes a timeline for that siting and construction or modification, which timeline shall include that such siting and construction or modification be completed by January 1, 2035.

(3) Priority

Any plan for the siting and construction or modification of transmission facilities described in paragraph (2)(B) shall prioritize—

(A) the use of grid-enhancing technologies;

(B) the use of existing rights-of-ways, such as highways and railroads, to site and construct new transmission facilities;

(C) the siting and construction of new transmission facilities on degraded land, including sites on the National Priorities List, brownfield sites, landfills, abandoned mine land, and contaminated or abandoned agricultural land;

(D) the siting and construction of new transmission facilities in a manner that expands access to renewable energy sources, including wind, solar, and geothermal sources;

(E) providing meaningful community involvement opportunities, including by conducting outreach to—

(i) environmental justice communities, including by conducting planning meetings, set at times and places to maximize the number of community members who can conveniently attend, with appropriate services, including translation and interpreting services and virtual attendance, in those environmental justice communities;

(ii) Tribal and Indigenous communities;

(iii) Tribal governments; and

(iv) relevant labor organizations; and

(F) the use of registered apprenticeship programs and prevailing wages, as determined by the Secretary of Labor in accordance with subchapter IV of chapter 31 of title 40, United States Code.

(4) Environmental review

Any project to site, construct, or modify transmission facilities that is conducted to comply with the reliability standard described in paragraph (1) shall be subject to the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.).

(5) Savings provision

Nothing in this subsection overrides or inhibits the authority of the Commission to require minimum interregional transfer between regions in a pair or grouping of regions other than a pair or grouping of regions described in subparagraph (A), (B), or (C) of paragraph (1).

(c) Consideration for national interest electric transmission corridors

In carrying out section 216 of the Federal Power Act (16 U.S.C. 824p), the Secretary of Energy shall consider designating as a national interest electric transmission corridor any area in which transmission facilities will be sited and constructed or modified pursuant to this section.

Section 5. Increased borrowing authority under the Transmission Facilitation Program

Section 40106(d)(2) of the Infrastructure Investment and Jobs Act (42 U.S.C. 18713(d)(2)) is amended by striking $2,500,000,000 and inserting $13,500,000,000.

(a) Definition of covered facility

In this section, the term covered facility means a facility for the generation, transmission, or sale of electric energy.

(b) Study and report

Not later than 1 year after the date of enactment of this Act, the Secretary of Energy shall conduct a study and submit to Congress a report on—

(1) the reliability, climate, and cost benefits of the interconnection of covered facilities in the United States with covered facilities in Mexico; and

(2) the siting and construction, or modification, of covered facilities that will bring the most cumulative benefits.

to ask questions about this bill.