Section 1. Short title
This Act may be cited as the Promoting Cross-border Energy Infrastructure Act.
(b) Importation or exportation of natural gas to Canada and Mexico
Section 3(c) of the Natural Gas Act (15 U.S.C. 717b(c)) is amended by adding at the end the following: In the case of an application for the importation of natural gas from, or the exportation of natural gas to, Canada or Mexico, the Commission shall grant the application not later than 30 days after the date on which the Commission receives the complete application..
(1) Repeal of requirement to secure order
Section 202(e) of the Federal Power Act (16 U.S.C. 824a(e)) is repealed.
(A) State regulations
Section 202(f) of the Federal Power Act (16 U.S.C. 824a(f)) is amended by striking insofar as such State regulation does not conflict with the exercise of the Commission’s powers under or relating to subsection 202(e).
(B) Seasonal diversity electricity exchange
Section 602(b) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 824a–4(b)) is amended by striking the Commission has conducted hearings and made the findings required under section 202(e) of the Federal Power Act and all that follows through the period at the end and inserting the Secretary has conducted hearings and finds that the proposed transmission facilities would not impair the sufficiency of electric supply within the United States or would not impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Secretary..
(d) No Presidential permit required
No Presidential permit (or similar permit) shall be required pursuant to any provision of law or Executive order for the construction, connection, operation, or maintenance of an oil or natural gas pipeline or electric transmission facility, or any border-crossing facility thereof.
(e) Modifications to existing projects
No certificate of crossing under subsection (a), or Presidential permit (or similar permit), shall be required for a modification to—
(1) an oil or natural gas pipeline or electric transmission facility that is operating for the import or export of oil or natural gas or the transmission of electricity as of the date of enactment of this Act;
(2) an oil or natural gas pipeline or electric transmission facility for which a Presidential permit (or similar permit) has been issued pursuant to any provision of law or Executive order; or
(3) a border-crossing facility for which a certificate of crossing has previously been issued under subsection (a).
(f) Prohibition on revocation of Presidential permits
Notwithstanding any other provision of law, the President may not revoke a Presidential permit (or similar permit) issued pursuant to Executive Order No. 13337 (3 U.S.C. 301 note), Executive Order No. 11423 (3 U.S.C. 301 note), Executive Order No. 12038 (42 U.S.C. 7151 note), Executive Order No. 10485 (15 U.S.C. 717b note), or any other Executive order for the construction, connection, operation, or maintenance of an oil or natural gas pipeline or electric transmission facility, or any border-crossing facility thereof, unless such revocation is authorized by an Act of Congress.
(1) Effective date
Subsections (a) through (e), and the amendments made by such subsections, shall take effect on the date that is 1 year after the date of enactment of this Act.
(2) Rulemaking deadlines
Each relevant official or agency described in subsection (a)(2)(B) shall—
(A) not later than 180 days after the date of enactment of this Act, publish in the Federal Register notice of a proposed rulemaking to carry out the applicable requirements of subsection (a); and
(B) not later than 1 year after the date of enactment of this Act, publish in the Federal Register a final rule to carry out the applicable requirements of subsection (a).
(h) Definitions
In this section:
(1) Border-crossing facility
The term border-crossing facility means the portion of an oil or natural gas pipeline or electric transmission facility that is located within 1,000 feet of the international boundary of the United States, measured from the point at which the facility crosses such boundary into the United States.
(2) Modification
The term modification includes a reversal of flow direction, change in ownership, change in flow volume, addition or removal of an interconnection, or an adjustment to maintain flow (such as a reduction or increase in the number of pump or compressor stations).
(3) Natural gas
The term natural gas has the meaning given that term in section 2 of the Natural Gas Act (15 U.S.C. 717a).
(4) Oil
The term oil means petroleum or a petroleum product.
(5) Electric Reliability Organization; regional entity
The terms Electric Reliability Organization and regional entity have the meanings given those terms in section 215 of the Federal Power Act (16 U.S.C. 824o).
(6) Independent System Operator; Regional Transmission Organization
The terms Independent System Operator and Regional Transmission Organization have the meanings given those terms in section 3 of the Federal Power Act (16 U.S.C. 796).